Showing posts with label electrical earthing. Show all posts
Showing posts with label electrical earthing. Show all posts

Thursday, April 21, 2011

Copper earth rod pictures

Here you can see a few pictures of electrical earth rods inside inspection chambers. These are all copper-jacketed steel rods with 16mm diameter.
=================
=================

Picture 1 – An earthing rod installed inside a precast concrete inspection chamber


The earthing system at this project was not yet completed at this point time.

However, the project was nearing the end of the construction period. Since this earth rod inspection chamber was by the side of a service road near the plant-room area, the installation of the rod and chamber needed to wait until the road crusher run has been laid.

This is to make sure that the chamber can be properly set to the finish level of the road.

Here the rod and chamber were already in place, just waiting for the final tar coating.

Picture 2 – A close up view to show the exothermic welding of the earth rod to the earthing PVC copper cable


Here I zoomed in a little bit into the earlier picture to show the type of bonding between the copper-jacketed earth rod and the copper earthing cable.

I personally always prefer that this connection is done using a suitable type of compression clamp.

However, this particular client has made it a rule that in all their building projects, the connections between earthing conductors and the earth rods must be done using a permanent bonding method such as the exothermic welding here.

This particular client was a very large organization who has to maintain many installations throughout the country. So I assumed that they were having some concern about the alertness of some of their maintenance teams on the ground to this aspect of safety.

If the concern was real, I would definitely agree with a permanent bonding like this. In this way there was minimal risk of quality at the connection being degraded over time.

Of course if there is a need to make an additional connection here in future for some reasons, then the task will be a bit difficult. But it can still be done although not in a very proper way.

Picture 3 – Connection of earth rod to earth cable using compression clamp



Here is an example of the connection using brass compression clamp. I had the contractor used this method first to try to persuade the client accept it. But they didn’t.

Picture 4 – A closer view of the compression clamp connection


Well, the workmanship of this connection could be much better. But since permanent bonding was insisted, the connection was changed to the exothermic type.

Copy right http://electricalinstallationblog.blogspot.com/ All rights reserved. - Copper earth rod pictures

Sunday, April 10, 2011

Switchboard earthing busbar

This post shows some pictures of the earthing busbar of a main switchboard. Click here to go back to the main post, Switchboard electrical earthing.
Photo 1 - View of the lower part of a main switchboard
You may be wondering why I did not stand back a little bit and take a wider view of the subswitchboard. The would give a nicer picture, right?
I however took this picture when the main switchboard (MSB) has already been located on its actual position in the electrical switchroom (LV Switchroom).
Usually the layout of an electrical LV room is such that the main switchboard is located near the wall of the room. The space behind the board is usually between 600mm to 1000mm between the back of the switchboard and the wall.
In fact 750mm is a more common space clearance for office and residential building. This of from my own personal experience. I do see projects where the architects were more generous.
In those cases you may then find that the clearance is between 1000mm to 1300mm.
Okey, back to the earthing busbar.
Here you see that the switchboard earthing busbar is located at the near bottom towards the rear door of the switchboard. This is a common practise.
The phase busbars are usually at the top part of the 2 meter plus main switchboard.
Here you may also notice the the photo shot was taken at the left end of the long switchboard. "Left" if you look at it from the rear.
So here you can also see how the busbar is mounter to frame or the chasis of the board. This is not how the phase busbars are fixed in place.
You can see the pictures of how they are fixed in future posts. Maybe if you browse around this blog, you may be able to see it already but I cannot be very sure if I have already uploaded a photo that contain this information.
Photo 2 - The earthing busbar of the switchboard
I just zoom in a little onto the busbar so you can see the details better.
Notice how the end of the busbar is fixed to the switchboard structureal frame. This way the structure is automaticalled earthed.
Notice also the green color sticker located on the busbar approximately at the middle of the panel opening.
Photo 3 - The green/yellow submain earthing cables and copper tape
The function of the switchboard earthing busbar is not only to ground the equipment and metal parts loacted on the switchboard.
It also serves as the feeder the grounding facilities that are needed by submain circuits taking supply from the particular main switchboards or cubswitchboard.
So in the above photo you can see four earthing connections: three from grounding cables with green/yellow insulation, and one from a 3mm by 25mm copper tape.
Each of these grounding conductor would be running along its respective phase and neutral conductors.
Photo 4 - The earthing connection to switchboard rear door (metal parts)
The specifications in the original article, Switchboard earthing, requires that all doors of the switchboard be properly connected to the grounding busbar.
So here is how it is done.
Note that it is a common practise to use spring washers to secure the cable ends to the bolt and nut.
It should be noted also that the cable lug should be a ring type.
A fork type of cable lugs should not be accepted.
Photo 5 - Branch earthing connections to the earthing busbar
When the specifications say branch earthing connections, this is what it meant.
The insulated green wires terminated to the switchboard earthing busbar is the earthing branch connections.
The provide proper and reliable connection to all live equipment and components on the panel or inside the switchboard.
Click here to go back to the previous post, Switchboard earthing.
Note: This anchor post, Free electric installation pictures , may contain a summary of the materials you are looking for. It can be faster than clicking through each post title at the Blog Archive. I started it long ago but never actually got around to finish it.
Copyright http://electricalinstallationblog.blogspot.com/ Switchboard electrical earthing

Wednesday, December 16, 2009

Switchboard electrical earthing

Following is a picture showing the earthing busbar of a main switchboard. Below the picture is a simple performance specifications for the grounding of the switchboard.
The are also two more posts on switchboard installation check and switchboard electrical tests. The latter is a general list of tests and inspections that are usually required of a major switchboard such as main switchboards and large subswitchboards.
Photo 1 - Earthing busbar of a main switchboard (MSB)
The earthing of an electrical switchboard shall be in accordance with BS 7430, and the color coding of protective conductors shall be in accordance with IEC 60646.
Switchboard earthing busbar
The switchboard earthing busbar shall be installed internally along the full length of the switchboard. The material of the busbar shall be the same as the material of the phase busbars. (See more photos: Switchboard earthing busbar.)
Equipment earth bar
Where the substation consists of 11 kV switchgears, transformers and LV switchboards, earthing copper tape shall be installed continuously along the full length of the substation.
It shall be connected to the main system earth bar at both ends using appropriate size earthing bolts with nuts and spring washers.
The earthing copper tape shall be made of hard-drawn high conductivity copper.
The cross-section of the earth bar shall be sufficient to carry the rated short-time withstand current of the switchgear for the allowable temperature rise and the time specified.
Internal branch earth connections
The branch earth connections made from the switchboard earthing busbar to the individual switchboard components shall consist of adequately sized copper strips, or green/ yellow striped PVC sheathed stranded copper conductor.
The termination lugs shall be of the compression type.
Earthing of metal parts
All metal parts of a switchboard where live components (such as relays, instruments, indicating lights etc) are mounted shall be earthed through branch connections to the switchboard earthing busbar.
Doors of the switchboard shall also be similarly earthed.
Frames of the draw-out circuit breakers shall be connected to the earthing busbar through a substantial plug type earthing contact.
Note: This anchor post, Free electric installation pictures , may contain a summary of the materials you are looking for. It can be faster than clicking through each post title at the Blog Archive. I started it long ago but never actually got around to finish it.
Copyright http://electricalinstallationblog.blogspot.com/ Switchboard electrical earthing

Wednesday, October 28, 2009

Electrical earthing system

Almost all electrical systems need an earthing system in order to operate safely. The following is an example of simple earthing specifications for electrical substations. This is just a simple specification and you may need to expand it longer depending on the type and complexity of the project you are going to use it in.
=================
=================

General
This section covers the earthing of all equipment and the provision of a complete earthing system including materials, electrodes and connections. The complete installation of the system shall be in accordance with the recommendations of the British Standard Code of Practice CP 1013:1985.

Electrical earthing Drawings
All the quantities of electrical earthing materials that have been detailed in the material schedules shall be treated as estimated quantities for tendering purposes only.

The contractor shall be required to prepare installation shop drawings and accurate schedules of materials shall be submitted as part of the shop drawings. The drawings and schedules shall be submitted to the Engineer for approval.

Electrical earthing System
A grid of hard drawn high conductivity copper tapes of cross-sectional area not less than 150 sq.mm, shall be installed by the contractor at each site in excavated trenches at 300 mm depth or, where permitted, in formed concrete cable trenches.

The frame of all electrical apparatus and structural steelwork shall be connected by branch conductors of the same cross sectional area to the substation main bar or where applicable, to subsidiary bars running to a group of equipment.

All isolator bases, post insulator bases, tension isolator strings, earth terminals and earthing switches, neutral current transformers, power transformers, surge diverter bases and where agreed with the Engineer, fences shall be connected to the grounding earth system.

Isolator and earthing switch operating mechanisms and circuit breaker control kiosks not integral with the circuit breakers shall be connected to the earth system by a branch conductor entirely separate from that employed for grounding the isolator, the grounding switch or the circuit breaker structure.

Electrical earthing points
The earthing point shall be of 16mm diameter copper-jacketed steel rod, supplied in 1500mm length and shall have provision for screw coupling with another standard length.

The copper jacket shall be molecularly bonded to the steel core to ensure that the steel core and the copper jacket are permanently bonded.

All rods shall only be driven into undisturbed soil.

Each electrode shall be provided with a complete set of approved non-ferrous clamps for connecting the earth rod to the earthing conductor.

 The rods shall also be provided with a hardened steel tip and cap for driving by means of a power hammer.

The number of earthing points required shall be determined at site after the letting of the contract.

Earthing link chambers and covers shall be provided and installed under this contract. The drawings showing the proposed arrangement shall be submitted by the Contractor for the approval of the Engineer.

The prices quoted in this contract shall include the driving of all earth rods, installation of link chambers, connection to earthing conductors, testing and commissioning to the satisfaction of the Engineer.

Precise locations for the link chambers and the interconnection arrangement will be decided by the Engineer when the complete test result of the electrical earthing system is known.

The combined resistance of all earth rods shall, if possible, be less than one ohm. The result shall not exceed three ohm under any climatic conditions.

Earthing Conductors

Conductors for interconnection between individual earth rods in any group and between groups shall have a cross-sectional area of 150 sq.mm.

There shall be at least two such connections from each electrode group to a link chamber.

Conductors for connection between the link chambers and the substation main bars shall have a cross-sectional area of 150 sq.mm. and at least two such connections shall be provided.

There shall be two separate connections between the neutral points of the high voltage systems and the link chamber of the earthing rods. Each of these connections shall a have a cross-sectional area of not less than 50 sq.mm.

The material of the earthing conductors shall be annealed high conductivity copper and shall be stranded. They shall be protected with an extruded PVC sheath of 1000 volts grade.

Earthing conductors shall be directly buried in the ground between the link chambers and buildings. Inside buildings they shall be fixed to walls and ceilings using appropriate copper saddles.

Alternative routes to run the conductors on cable racks or in trenches can also be allowed provided appropriate methods and accessories are to fix the earthing conductors are used.

Jointing and Bonding
Prior to jointing (soldering) of the earthing tapes, the surface of the tapes shall be cleaned and thinned. The area of the joint shall be riveted with copper rivets.

There shall not be less than four 3mm rivets used for each joint.

Only non-corrosive flux shall be used in all soldered joints.

Alternative methods employing chemical welding or high compression joints or clamps, may be permitted subject to the approval of the Engineer.

Any alternative method of joints shall only be considered after full details are officially submitted and no work employing them shall commence prior to the official approval from the Engineer.

Tests at Site
The contractor shall carry out all necessary tests to determine the soil resistivity at each area of the sites.

The contractor shall also be fully responsible for proving that the electrical earthing systems comply with the specifications.

It is the contractor’s responsibility to measure the resistance of each electrode installation and the resistance of each complete electrical earthing system without additional charge.

A complete method statement covering the installation procedures, the inspection checklists and the full testing procedures shall be submitted to the Engineer for approval prior to the commence of the actual installation work.

No work shall commence prior to the official approval of the method statement.

Copyright http://electricalinstallationblog.blogspot.com/ - Electrical earthing system

Tuesday, October 27, 2009

Home electrical earth installation

This post is about home electrical earth installation or home electrical grounding. Some people call it electrical ground, or earth grounding, electrical earth, or just grounding or ground. In fact, I have come into some really funny names for the electrical earth.

=================
=================

That is because the earth has no mass, and it has no quantity. It is actually a function. An electrical current has no mass, but it has a quantity. Your house switched socket outlet is rated 13A, for example. That is 13 Amperes, a quantity that is definite and measurable. The more enlightened ones will say that is the quantity of electrons that is measured.

Unlike current, many people seem to have given up trying to understand this electrical earth, never mind those who never care in the first place.

Whatever the real reasons are, this situation has resulted in a very serious problem: many people are not able to use electricity safely. They allow their loved ones be exposed to unnecessary risks and dangers.

Look at the nice diagrams that I quickly prepared for you below. Picture No 1 is how the small house looks like at the cross section view from the right side of the house. Note that the main entrance is on the left side of the drawing. Picture No 2 is the house electrical layout. I used the same picture (plus a little additional information which I hope you can figure out on your own – this is the kind of materials that nowadays they put inside the books on urban survival skills) in the earlier post to explain on how to read the house electrical wiring, the electrical symbols used, and a simple guide on how to check your house electrical installation from safety view point.

Picture No 3 is something I cooked up to show you an overall view of the electrical system involved in the flow of electricity from the substation to your house. This diagram is very important for those who do not have the time to think about technical stuff on electrical system, but have been very concerned about the risk of electrical shock that may be present in their house. Take your time to study this diagram. It is actually nothing more than a flow chart actually.

While Picture No 4 contains some additional details about “the earth” for your house wiring. This is the earth chamber. This is the part that help the wiring discharge the current to where it belongs when some malfunction occurs to the wiring or the appliances so your house occupants can stay safe. You may have seen this at your house, but only the top part on the surface is visible. So now you can know how it looks inside and underneath.

Please note also that the lightning protection also use the same thing to discharge the lightning current during the lightning strikes. Sometimes it is called the lightning rod. So your house usually has at least two of these earth chambers: one for the electrical and one for the lightning protection system.

That is the short brief about the pictures that I have uploaded to help you to understand what the electrical earth is.

Now let us start the main lesson. I put all the four images first and the explanation after them.

Picture No 1 – Incoming supply and earth chambers

Picture No 2 – Electrical layout drawing

Picture No 3 – Fault current path

Picture No 4 – Details of the earth chamber

1. Home electrical basics

We need the earth installation because we have electricity in our house. So we must understand the home electrics first before we can really understand the earth. You can visit this post, Home electrical wiring, symbols and checking, to read more details of this subject.

Picture 1 shows how the electric supply is brought to the house. It came from a substation somewhere and transported through cables to your house. Here it came through the overhead cables tied to the top of electric poles along the street of the residential area. I am sure most of us have seen this and how the cables are brought to the energy meter at the front wall of the house. Anyone who haven’t seen it can see the pictures of them somewhere else in this blog.

Now look at Picture 3. The source of the electricity is at the substation on the far left of the picture while location where it is being utilized is on the far right. If you see the pretty girl then you can see that she was being electrocuted. That what we all don’t want and that is why you need to watch the diagram carefully. I will not write too long today because it’s already 1.00 AM and I have to go to work tomorrow. However I will update this post and write some more details. By the time I am finished with this post (after a few updates probably) you will understand enough to take the necessary care and precautions at home with regards to electricity and electrical appliances.

For now just observe that the electric current from the power transformer at the substation flows along the path indicated by the direction of the red arrows pointing to the right side of the diagram. When it arrives at the four circuit breakers on the electrical panel, it travels through the lowest circuit breaker because that is the circuit that is supplying the socket out where the washing is connected. Normally the current travel back to the star point of the transformer through the second wire which is the lower black line from the washing machine. I did not put any arrow to indicate the return path of the current. But that path will go to the neutral busbar (the one with the label “E” inside the electrical panel). If you trace the connection, it will go back to the neutral point of the power transformer.

But the diagram shows that there is another two alternative paths the current can take to go back to the transformer star point. The first (or the second because the first is through the neutral wire) is shown by the red arrow right below the washing machine. You can see the black line connecting to the machine’s metal body. The connection is shown here by the black dot at the intersection point.

So the current can travel through the earth wire shown by the red lines as I said above. This is actually the third wire in your house wiring, which is the green wire. If your house wiring is concealed inside the wall, you may have seen the green wire inside the extension cord or at a damaged plug where the cover has been broke. That is the third wire shown by the red line below the washing machine. This path will follow the wire and arrive at the earth busbar (with the label “E”) inside the electrical panel or distribution board. This earth busbar is located near the neutral busbar (label N).

If the neutral busbar is connected to the transformer star point through the neutral return wire, the earth busbar is connected to the earth camber that I mention at the beginning of this post (see Picture 4). The black wire labeled “Electrical panel earthing” is what we called a grounding conductor or the earth conductor. With this earth conductor the machine is solidly connected to earth. Yes, connected to the real earth mass. The earth chamber is just an enclosure and a cover to protect the components inside and underneath it which are a long copper rod with some very important connection accessories inside.

Back to the ground wire path. Under normal situation the electric current inside the washing machine does not flow through this path (the third path). It will just flow through the neutral wire to flow back to the transformer star point. However like everything else in life, nothing last forever. The most expensive machine that you can buy may have a five year warranty sticker on it and the vendor’s office guaranteed that you will have their best technician knocking your house door within 15 minutes of your call.

However the girl in the diagram may not be alive long enough to make the call. The line from the black dot below the machine to the earth busbar follows such a zigzag route. I could have made it straight and direct, but I didn’t. Some of you may have a pretty good idea why. I may need one whole post just to explain the “why”.

Okay, so nothing last forever. One day one of the components and parts inside the machine will fail. If the failure leads to poor insulation of live parts, then a small amount of electric current may leak to one of the exposed metal parts of the machine. That metal part will get energized or “live”. This is why we need the earth wire connection there. The exposed metal parts are not supposed to get “live”. That’s why they are exposed to touch. So the voltage they carry due to the leaked current cannot go back to the neutral star point through the earth wire. With the earth wire, that voltage has a path to escape to which is straight to earth.

So what? The metal part gets energized and it has the current flowing through it and to earth. People will still be touching a live metal, right? Right! But that metal and the designed live metal inside the machine have a very big difference. The bonded exposed metal is at the same potential as the earth which is 0 volt (that is “zero volts”). And the girl there is also at zero volt, the potential of the earth. Since both the girl and the exposed metal are at same potential, the current will not flow through the girl, or the flow will extremely small. (That is in theory. Many other factors are also involved in real situation).

The above is point no 1. Another point is the solid connection will minimize the resistance between the exposed metal to earth. Since the current is inversely proportional to resistance, a minimum resistance will give maximum current. This aspect is utilized by our ancestors to create a protection device that can protect the girl. The leaked current will be detected by the devise and it trips the connection of the supply to the machine. Therefore the will be saved before the voltage rise up high enough to cause serious injuries. The established setting of this current has been 30 mili-Amperes. This is what the experts in this field have come to follow, and this is the label that you can see near the earth leakage protection devise in Picture No 3.

Which devise? That is the ELCB (earth leakage circuit breaker). It’s in side the electrical panel. On the diagram also it is labeled “ELCB”, with “60A DP” and “(30 mA)” label just below it.

The ELCB itself is a long topic so I will save it for another time. But if you cannot wait, my earlier posts have already some information on how it works. I will explain more in future posts. (UPDATE: Visit ELCB - Home Electrical Shock Protection and also ELCB circuit for a much more detailed information about the ELCB circuit breakers.)

So now do you understand why we need the electrical earth there? Why having it properly working is an absolute necessity? A matter of life and death? Good.

I have not forgotten that I titled the post “Electrical earth installation”. And I have not even started the installation part of it. I was absorbed in the why. The how part of it will have to wait for another time. I will continue on this topic as an update to this post. There will be other posts on the earth installations, but I also need to make this post complete as what the title says. Some readers may not have the time or desire to click to another post to get to what they hope to find.

See you soon.

Note: Visit this post, Free electric installation picture, to see more pictures, diagrams and drawings of electrical installations. I started it some time back as an anchor post, but got around to really finish it. It can be much faster than searching through the BLOG ARCHIVE folder.

Copyright http://electricalinstallationblog.blogspot.com/ All rights reserved – Home electrical earth installation

Friday, July 17, 2009

Temporary Electrical Installations

This post will present you with pictures of temporary electrical installations, the temporary switchboards (at this post, Temporary electrical switchboard), temporary electrical DB, temporary cables and poles.

The post is open ended. I will keep adding more pictures and comments when I find something that I think the readers will be interested in.

Someone also commented that I have yet not uploaded any picture on temporary lighting.

Well, now you have a few of  the pictures at this post,  Temporary site floodlights. There is also more information on site lighting here, Temporary lighting installation.

I have also just sent a new anchor post,  Free electric installation pictures, to partially fulfill a few requests to have all the pics at one place.

So if construction site’s temporary electricity supply is a subject of your interest, keep checking this post every few weeks, you may find new information that you can use.

-----------------------------------------------------------------------------------------------
RELATED POSTS: (a) Electrical DB installation; (b) Electrical injury pictures;

.........................................................................................................................

For readers who have visited this site before, you can see that this post keeps changing. That’s because I need to adjust the layout and some contents here and there so the newly added information can fit in and also to make the various content more coherent.

One other thing, if you have the time, check out the following link. It is a link on how to convert your car into an electric car at minimal cost. It is a way we in the electrical industry can contribute in the global effort to save this planet. In any case, it can save some significant dollars of our daily transport costs. Check it out. It’s a good reading.

Content:

Section A. First case – 20 floors of temporary electricity supply without the electrical grounding.
Picture 1 – Temporary switchboard, temporary DB, temporary cables, temporary extension cords, temporary sockets.
Picture 2 – Another temporary DB (Picture quality not so good. Sorry…)

Section B. Another DB – Temporary electrical panel, temporary cables and extension cords.
Picture 3 – Temporary distribution board – Right view
Picture 4 – Temporary distribution board – Front view
Picture 5 – Temporary distribution board – Left view

Section C. Site temporary electric supply – The risk

Section D. Another case of the electric supply without the earth grounding.
Picture 6 - Electrical panel location (Click on the picture to see full size)
Picture 7- Electrical panel inside view (Click on the picture to see full size)
Picture 8- Earthing copper bar without connection to earth (Click on the picture to see full size)
Picture 9- Incoming 4-core twisted cable without earth (Click on the picture to see full size)


Section E. A simple example of temporary earth
Picture 10 – Temporary electric supply: The complete system
Picture 11 – Temporary cables, temporary meter, temporary distribution board, temporary earth wire and protective PVC conduit.
Picture 12 – Temporary earth grounding


Section F. Site power distribution and equipment

The supply equipment

The distribution system
Picture 13 – Temporary electric poles
Picture 14 – Accidents on electric poles

Section G: Is there a foolproof system for a site temporary power?
The weaknesses of RCD (or ELCB)
Diagram 15 – Three- phase reduced low voltage supply system
Diagram 16 – reduced low voltage supply system (single phase)


Section A. First case – 20 floors of temporary electricity supply without the electrical grounding.


Today I am going to share with you a picture of one of the most important parts of temporary electrical installations in construction works, that is the temporary supply sub-switchboard, distribution board and their cabling.

Below is the picture of a temporary electrical assembly. It was taken at one of my projects a few years ago. What you see in the picture is the floor temporary sub-switchboard, which sits on the left of the assembly. Next to it is the temporary DB with an on-board three phase isolator and a few 13A switched socket outlets.

Picture 1 – Temporary switchboard, temporary DB, temporary cables, temporary extension cords, temporary sockets.

Temporary Electrical Installations Board Image 1

The project was a multi-storey residential building and the temporary supply was taken from the temporary main switchboard at the ground floor. The authority's meter panel was installed at the main switchboard. So the twisted 4-core submain cable was run from the main switchboard to each sub-switchboard at individual floors (one sub-switchboard for every three floors actually). Since it was a 21-storey condominium, seven subswitchboards were installed. From each sub-switchboard, cables were run at high level to distribution boards at various locations at the three floors in its coverage.

Back to the picture… So what is so special about the electrical board assembly in the picture? This is one example of the usual practices in the installation of temporary electrical supply at construction sites in our country. Not all construction sites are like this example, of course. Many job sites practise very good safety standards and I can personally testify to that, but quite frankly the practise shown in the picture is quite common. And in this case I have seen one situation that I have never seen in my entire 18 years of involvement at construction sites. I apologize the picture may not be very clear, but I hope you can see that the incoming cables to the floor sub-switchboard is only four-core. It has NO EARTHING at all.

I joined the supervision team while the work was already quite advanced with only a few month left to the completion. The temporary electrical supply has been in operation for almost a year. The electrical sub-contractor has also been on board for many weeks. Yet the electrical supply distribution from first floor to top floor at Level 21 has no earthing. I was shocked when I notice this on my second day at site. It was unbelievable. Some unlucky workers could have died from this oversight.

The 25 by 3 mm earthing copper tape was finally installed later, after many days of my urging them to do it. The distribution boards and the temporary cabling were also much improved.

As you can see, apart from the earthing conductor, obviously there were a few more things that were wrong with the distribution boards, the cabling and the plug and sockets in the picture. Maybe we can talk again about these in my future posts.

For now I just wish to emphasize the importance of checking the temporary electrical supply installation at your construction sites. Do not assume that the main contractor of a RM230 million building project will have enough people to look at safety matters as important as this one.

More Temporary Electrical Installations

I have also attached below two more pictures of temporary distribution boards just for the fun of it.

Picture 2 – Another temporary DB (Picture quality not so good. Sorry…)

Temporary Electrical Installations Distribution Board Image 2



Temporary Electrical Installations Distribution Board Image 3

These temporary electrical DB are also located along the main access route inside the building under construction. Exposed, without barricade, without any protection at all. This is how you can get electric shocks.

That's it for now. When we meet again I will show you a few more pictures of electrical installations from my previous projects and maybe we can learn some things from them.
That's it for now. When we meet again I will show you a few more pictures of electrical installations from my previous projects and maybe we can learn some things from them.


Section B. Another DB – Temporary electrical panel, temporary cables and extension cords.

These pictures I have already posted on my other blog a few months. It’s a new blog I just set up but I don’t have much time to spare on it. So it’s not drawing much traffic. So I thought I might as well put it here so it can be of some use to someone.

Below you will find a few pictures on a temporary electrical panel, sockets, plugs and extension cords. I have added a few comments below the pictures on aspects that I think is important. Further comments will be added when I think of something readers may be interested to know.

Picture 3 – Temporary distribution board – Right view


Temporary Electrical Panel Image 1
Picture 4 – Temporary distribution board – Front view
Temporary Electrical Panel Image 2
Picture 5 – Temporary distribution board – Left view
Temporary Electrical Panel Image 3


Is there anything wrong with the electrical installation in these pictures? The temporary panel seems to be quite new and definitely in a good condition.

You may question about the mounting method for the panel. But this is a temporary panel for a construction site. At times, the subcontractor needs to move the panel from one place to another every few days. So fixed wall mounted method is not a practical choice this circumstances.

Yes, you may want to suggest that the mounting stand be made of a much better material and design. That I would agree.

The supply temporary cables to the panel seem to be four single core cables. I do not know what size just by looking at the cable from a distance, even though an electrician might be able to give a good guess. Four core means four phases plus one neutral.

You can also see two very good-looking wires with green insulation twisting along the four-cable bunch. These must be the earthing wires, or Circuit Protective Conductor to be precise. Is the total cross section sufficient of the earth wires sufficient? I am a bit rusty on this nowadays. But temporary electrical supply only needs residual current protection as the shock protection. The green wires seem like 4 square mm. Two of them will give 8 sq.mm. I think that should be enough. Of course the required cross section of the earth cables depend on the distance of the temporary panel to the earth electrodes.

That covers the electrical panel and the incoming supply cables. Now let us look at the outgoing circuits from the panel.

First the socket outlets, or the receptacles as the Americans say it. They seem to have the original SIRIM sticker on each of the sockets. In any case all the sockets are new, so there should not be much issue about them. However what has been plugged into each of the sockets is a different matter.

The appliance connected to the right socket of the lower row should be okay. I think it's the charger for a walkie-talkie. All factory-manufactured and all new.

However, the cords connected to the other four sockets may have some serious safety issues. I will add comments on these in the near future.

Have a nice day.



Update Jan. 2010: You can see pictures of 11kV switchboards at my new post Hospital LV Electrical Installation.



Section C. Site electric supply – The risk

It has always been a challenge to provide the electric supply to the site people safely. Construction sites are among the most challenging environments to the safe use of electricity.

A lot of works are done outdoors, in all sorts of weather conditions. Wet and damp conditions present very high risks of severe electric shocks.

The workflow of site works is constantly changing as the construction work progresses. Therefore, the temptations to improvise the electrical distribution system are often too great to resist.

Routine construction activities, the demolition and excavation works may all result in damages to both the temporary supply and the newly fixed permanent supply systems.

When the activities at a site are at its peak with hundreds or thousands of workers (not to mention construction vehicles and machineries), the site usually become very congested. This sort of situations makes the control of risks very difficult. Temporary cables and electric construction tools and equipment are very likely to be damaged by the movement of heavy machines and materials.

The people who use electricity at site have various needs, and sometimes conflicting interests and expectations. The workers and team leaders themselves work for different subcontractors and suppliers. In order to maintain any reasonable degree of safety and control of risks, a effective site management is an absolute must-have for the site main contractor or the client’s people who are in charge at the construction site.

Due to the nature of construction works, a risk-free environment is impossible to attain most of the time. However, some risks can be avoided by careful planning before the work commences at the site.
-------------------------------------------------------------------------------------------------

Section D. Another case of the electric supply without the earth grounding.

This is another case of missing electrical grounding that I already published in my other blog.

The following pictures of a temporary electrical panel show another common type electrical hazard at construction sites. I took these photos at a building construction site about four months ago.

This panel was located under a shade at the concrete mixing station of the construction site. As you can see, the location of the electrical panel was full of water. No, it was not due to rainwater. The location was always that way, because the plant consumed a lot of water daily. The situation presented a very high risk of electrocution not just to the worker operating the concrete mixing plant, but also to other workers.

Someone at the site told me that the electrical panel was too high above the water. So there was not really much risk. What do you think?

Picture 6 - Electrical panel location (Click on the picture to see full size)


Electrical Panel Image 1


I opened the electrical panel door to check inside (See Picture 7). The panel was a good quality and relatively new. The internal wiring inside the panel was also done nicely and it was neat.

But wait.... Where is the earthing to the panel? There was good earth wiring inside the panel - the green wires. All neatly run and properly terminated to the copper earth bar. However, the connection just stopped there. There was no outgoing connection to earth (See Picture 8).

Picture 7- Electrical panel inside view (Click on the picture to see full size)

Electrical Panel Image 2




Picture 8- Earthing copper bar without connection to earth (Click on the picture to see full size)
Electrical panel Image 3


I checked the incoming twisted cable. It was a four-core. No earth cable anywhere (See Picture 9). I checked around the panel to see if the person who installed it used a different conductor and run it direct to earth somehow. Nope, no other conductor installed.

The conclusion? The electrical panel was not earthed at all. So what happens when there is a considerable leakage current? What protects the worker at the concrete mixer machine there, especially with the wet condition there? Sadly to say... no protection at all.

Feeling exasperated, I checked inside the electrical panel again. Surprise... there was not even an earth leakage circuit breaker there, or any other type of residual current protective device.

Picture 9- Incoming 4-core twisted cable without earth (Click on the picture to see full size)

Electrical Panel Image 4


I have to go now. I will add more info to this post in the near future. I know there are questions in the minds of some of the readers relating to the electrical installation shown in these pictures. The electric shock protection issue can be tricky sometimes.

Until next time...

Section E. A simple example of temporary earth

The safety of an electric supply often depends on the existence of an effective earth. It is the responsibility of the person in charge of the construction site to ensure that the earthing of the electric supply system is effective. The site’s electricity supplier (the electric supply authority) has nothing to with this part of the electric supply.

Many electricity supply authorities use protective multiple earthing (PME) system. In this system the electrical system’s neutral and earth are combined. When this system is used, all metalwork including structural metalwork must be bonded together in such a way to make all metal parts electrically continuous.

However in most real life construction sites, this bonding is hard to do and almost impossible to maintain properly throughout the duration of the construction period. So usually, the public utility supplier will not connect the supply until an alternative electrical earth is provided and fully tested. They also insist that evidence of the earthing test results endorsed by a competent electrician is submitted together with the completed application forms for the temporary electricity supply to the site.

Several methods are used to provide the alternative electrical earth. The most commonly used method is to use an independent earth electrode installed at the location near the main intake temporary switchboard (this is usually the location where the temporary meter is installed). This will ensure that the protection fuses will operate and disconnect the site electrical installation from the incoming public supply in the event of a fault. This disconnection is an absolute must in order to minimize the damages to the site’s electrical system due to the fault and also to prevent the fault from spreading upstream to the electric supplier’s distribution network. The latter is the main reason the electricity supplier is worried about this aspect of the temporary installations.

Picture 10 – Temporary electric supply: The complete system


I will devote one whole post in the future for this subject of earthing. But for now I have a few picture of temporary electrical grounding for your viewing pleasures. I seek an apology from those readers who already have some electrical knowledge. These pictures are not for you guys. They are too simple. However for those managers and construction people who have always been intimidated by those colleagues on these sorts of issues, let me assure you that if you understand what these three lousy pictures say, then you already understand what an electrical grounding is.

Picture 11 – Temporary cables, temporary meter, temporary distribution board, temporary earth wire and protective PVC conduit.


Picture 12 – Temporary earth grounding


Now lets start with picture 10 (You may need to click on the picture to see it in full size). The black case on the wooden panel there the temporary electric meter supplied by the electric authority. Below it in white PVC casing is the temporary distribution board. You can also see coming out downward from the distribution board a piece of wire in green insulation and this wire goes straight into a two meter length white PVC conduit, and (if you watch it closely) it comes out of the vertical PVC conduit at the bottom and goes straight into the concrete floor just beside the plywood partition wall. All these you can see much more clearly in Pictures 11 and 12.

Back to the black energy meter. Above it you can see two lengths of black insulated cables coming down from high level (below the roof level of the temporary wooden structure). One cable terminates at a black piece of component just above the meter, while the other one terminates at a cheap white plastic terminal block. The two components each have a cable of the same size coming out at the bottom connection and terminate at the temporary kilo-watt-hour meter.

Now lets get a little bit more technical. This is what we call a single-phase electrical installation (a three-phase supply would have four black cables coming down from the roof level – three phase cables and one neutral cable). So the incoming supply from the authority is also a single phase supply (we apply single-phase supply, so they give us a single phase supply).

An electric supply from the authority can be one of a few types. The type as recorded in the pictures is the single-phase two-wire type (three-phase 4-wire if we apply three-phase supply). This type will have two incoming cables from the authority’s distribution network – one live or phase cable and one neutral cable. Other types may have three incoming cables from the distribution network for the same one-phase supply – the same live and neutral cables, plus a third cable, which is the earthing cable.

Now as I said earlier in this post, a construction site really needs an independent and reliable earthing, an electrical grounding that is not dependent on any third party’s grounding or even the electricity supplier’s grounding. Failure to provide this can result in fatal injuries from electric shocks, even multiple casualties in a single accident. Never mind my emotions on this (if you can sense them), but an electrical accident is that dangerous and electrical shocks can strike silently without warning.

Because of the need for that independent and reliable earth for the temporary site supply, the green electric cable is installed below the white PVC distribution board (Picture 11 shows this clearly). Without this cable, the electrical system can still work. The workers can still use their tools and do a good job for their employers so the construction venture can end up being very profitable for the shareholders of the company. But one fine day, an extension cord that carries current to the electric drill one of the workers has been using gets injured, exposing the live wire to an unintentional contact with any of the workers around the area. Being hard at work, the workers bodies and clothes are usually very damp or very wet with sweat. One accidental contact at any part of a workers body with the exposed live conductor of the damaged extension cord, then you will severe electric shock injury, even death is highly likely depending on where on the worker’s body the contact to the live wire happens. If the contact is at the hands, then the electric shock current will travel through the chest and the workers heart before going down to the legs and the ground. Then you may have a case of fatal injuries there.

Sorry for the diversion. This electrical earthing matter is so simple that I have to drag the stories into the injury aspects to make it a bit longer ;-)).

Not only it is simple, it is also plain cheap and low cost. Look at the picture again. You have a short length of the green wire and two meters of the white PVC pipe. Wait… I know what a few of you are thinking… Yes, there is copper earth electrode in the concrete, which goes straight down below the concrete about 1.5 to three meters into the ground.

The example that I use here is a very small installation, so it looks simple. This wooden structure only uses a few amperes. However even for a large installation, the grounding is relatively just as simple.

The point that I am trying to make in this section is that providing an independent and effective earth is not a challenge at all in most situations. So, do not risk human lives just to save some construction cost there.

Section F. Site power distribution and equipment

The supply equipment

Equipment selected for use in a site temporary electric supply distribution need to be designed for use in the environment it in is going to be operated in. During the selection process, the most important is to make sure that the manufacturer’s restrictions of use are considered. For example a sub-switchboard that need to be moved frequently, left exposed under sun, and rain during operation must necessarily be of adequate IP rating.

The construction of the equipment must also be robust enough to withstand the damage caused by the rough treatment at the construction site.

Most of the time, equipment purchased for use at a project site will be transported for use in another project or work locations. Therefore, it needs to have provisions for frequent loading and unloading, transport and storage while throughout all these it cannot be damaged to the point of becoming malfunction and unsafe for use. Under the pressure of worksite demands, even a good site electrician tends to improvise on the safety aspects site electricity supply. With damaged equipment, the risks are compounded even more.

The equipment selected also shall include the provision for isolation of supply and facilities for locking the switches. This is especially important main switchboards and sub-switchboards where the locations of the board and the local distribution boards are quite far away and not within the line of sight.

The distribution system

The distribution system is the system of cabling and equipment that are arranged to distribute the electric power to the various machines and current using locations throughout the construction site. This temporary distribution system will be removed after the construction work is completed and the permanent power supply system is commissioned and operational.

The location of the switchgear and metering apparatus must be secured in terms of security from unauthorized access and safety from damage and the effects of the environmental factors. Access to the switchgears and the main isolation switch must be accessible at all times in case of emergency.

Just because the supply system is temporary does not mean it can be assembled without all the proper engineering calculations and considerations required of a permanent system. Fuses, circuit breakers and cables all must properly selected and sized.

Many practices shown in the pictures of temporary installations above are bad practices. If contractors are allowed to provide these bad installations on site power supply, accidents whether in the form of damaged equipment, fires or electric shock or even electrocutions is bound to happen sooner or latter. Makeshift arrangements such as unprotected wiring, twisted or taped cable joints are often dangerous and cannot be accepted. All the temporary installations works must be done in accordance to the appropriate standards.

Site distribution cables must be properly located. They should not be installed where they are likely to be damaged by the construction activities or vehicles. Picture 13 below shows an example of a site distribution cabling running on temporary electric poles. This method of installation is fine but here they are run across one of the main road within the construction site. The next picture (Picture 14) shows the temporary cables on the ground. Only a few minutes earlier, an earth moving tipper truck accidentally hit and dragged the overhead cable while unloading the earth for a drainage work next to the temporary poles. There were workers nearby when it happen, including me. Luckily, no one was injured.

The above accident could have been prevented if the stretch of the cables crossing the construction have buried in a G.I. pipe just two or three feet below the road. With all the construction machineries at the site, these could have been done in a matter of one or two hours. However, here the main contractor chose the easy way and just installed the whole stretch on poles.
Picture 13 – Temporary electric poles

Picture 14 – Accidents on electric poles


Section G: Is there a foolproof system of site temporary electricity?

RCD (or ELCB)

RCD (residual current devices) or ELCB (earth leakage circuit breaker) is not an ideal device for use in the tough environment of construction sites. It may not even be possible to maintain the integrity of the housing where the RCD devises are housed in.

It is also not the kind of devices that can be fitted on portable equipment, which usually are subject to mechanical shocks and vibration.

Electric shock protection based on RCD alone has many weaknesses. It cannot guarantee safety.
a) When an RCD malfunctions or it fails to operate, this failure can go unnoticed so the affected workers are unaware of the dangers awaiting to turn into accidents.
b) The RCD only protect against faults to earth, and it required sufficient bonding to earth for operation. It cannot operate when there is no earth connection, for example, when current passing from live to neutral. This type of situation is still dangerous: the workers can still get electric shock, injuries or even electrocution even though the RCD is working properly.
c) The use of RCD will not make the system safe if it is not properly designed, properly installed and adequately maintained. The popularity of RCD may have been due to difficulties to obtain low earth resistance on many installation conditions. However, RCD is not a substitute for reliable and efficient earth grounding.
d) RCD designed for electric shock protection have a rated tripping current of 30 mA. At sites where temporary load requirements are higher, installing a 30 mA at the point of intake (like an ELCB installation in a house distribution board) will lead to frequent unnecessary tripping, shutting off the supply to the whole site.
e) Electrical loads at construction sites consist of tools and equipment that have high leakage currents. This factor has led to many ‘nuisance’ tripping of the supply. These are also unwanted tripping that frequently lead to the RCD devise being defeated in some by the workers involved, leaving the whole supply system with a shock protection.
f) RCD can be chosen to be very sensitive to small current leakage, and trip fast enough to avoid serious injuries. However, with this principle, it only limits the duration of time that the current flows in the event of shock, it does not limit the magnitude of the current flowing. If the devise fails to operate, the current will continue to flow continuously. Even low shock current if allowed to flow continuously through the body can cause serious injuries.

Reduced Low Voltage supply

Most of the time the electric shocks that occur are between the live parts and earth, which are the results of damaged cable insulations, faulty power plugs, or faulty or damaged equipment. Whatever is done to the electrical system, or the electric shock protection to reduce the risk of shock to people, the potential is always there. RCD itself is a active electromechanical system that can fail. It effectiveness requires an effective earth which can be hard to maintain in a real life construction sites. While the scope of protection covered by the device still have gaps, that is left without shock protection (between live and neutral).
Fortunately, there is one system that has been proven almost foolproof against electric shocks at construction sites. It is called the reduced low voltage system, where the supply voltage is stepped down to a level which is practically safe without depending too much on an active shock protection, or a sophisticated system that is hard to implement at construction sites.
This system reduced the 415/ 240 volts supply voltage to 110/64 volts for a 3-phase supply. If only 1-phase supply is needed, then a 240/ 110 volt center-tapped transformer is used to reduce the single phase voltage to 110 volts with the electrical grounding connected to the center of the secondary transformer coil. This will present a maximum possible risk of only 55 volts to the users of the electricity instead of 240 volt (or 415 volts for 3-phase) as I the original 415/240 volts supply.
Technical studies that have been carried out have shown that the maximum indirect contact touch voltage to earth is only 40 volts. This is below the danger voltage as specified by the IEE Regulation. Even the SELV (safety extra low voltage system) as specified in the regulation is 50 volts.
The following diagrams show the basic configuration of the reduced low voltage supply system.

Diagram 15 – 3-phase reduced low voltage supply system


Diagram 16 – single-phase reduced low voltage supply system


(c) copyright http://electricalinstallationblog.blogspot.com Temporary Electrical Installations