Wednesday, January 6, 2010

How you get electric shocks

I have sent a lengthy article to this blog some time back on how a person can happen to get electrical shock. However, some readers complained that it was too long that they have difficulties finding what they want to read about. Therefore, I have decided to write a few short articles on subtitles covered by that post for the benefits of casual readers who are looking for only certain very specific issues. This post is the first of those subtitles.

Look at the four beautiful diagrams that I just created below.

Diagram 1 – Touching live electrical wire and the neutral wire



THE SIMPLE LOGIC OF ELECTRIC SHOCKS

Electric shock happens when a certain amount of electrical current happen to flow through a person’s body for whatever reason. The human body has not been designed to conduct electricity above a certain current level or miliamperes. The above-mentioned post on electric shock protection gives a detailed description on the levels of current that can cause injuries and electrocutions. You can read it here, ELCB - Home Electrical Shock Protection, if you wish to know them in more details.
What happen when the electrical current flow through the body? At a lower level, the current interferes with the nervous system. That is why when someone accidentally holds a live wire with her hand, she may not be able to let go of the wire. In fact, her fingers may even grip the live wire tighter, resulting in a much better contact between the hand and the wire. This will result in lower contact resistance that will further increase the current flow and therefore more serious injuries. If you visit this post, Electrical injury pictures, you can see the pictures of how serious the electrical injuries can be.

The higher the shock current, the more severe the injuries

If the shock current is higher, then the body tissue where the current flows will get damaged. The higher the current, the more serious the damage. At 10mA, the victim may still be able to control his arm and instinctively release the electrified object or wire he is holding. However that is about the maximum shock current that he can handle. If the shock current is higher, he would lose control of the arm. The hand grip on the tool may get stronger, resulting in higher current flow.

At 100 mili-amperes (that is 0.1A), the victim faces a certain death if he sustains that level of shock current flow for 2 seconds or more.

The degree of injuries depends on which body parts the shock current flow through

The path where the shock current travels through the body also will have some effects on how serious the injuries can be. If a person touches a live wire by his right hand while standing on a grounded metal part, the electric current flow through from the live wire through the hand, the arm and shoulder, the chess, legs and down to the metal part. In this case, the current can damage the victim’s heart while flowing through the chess. At 30 mili-amperes, the victim may even stop breathing (respiratory paralysis).

The higher the voltage, the more serious the injuries

The higher the voltage, the more serious the resulting injuries. At 600 volts, the electric shock current can be as high as 4 amperes. This level of current can seriously damage the victim’s heart and other internal organs. The skin where the body makes contact with the live wire can be burned. The tissue damages are so serious that a limb on the path of the flow of the shock current can come off the victim’s body.

The longer the current flow through the victims body, the more serious the injuries

As I said above, at 100 mili-amperes, the victim faces a certain death if that level of current continues to flow through the body for more than 2 seconds. This is very useful information for those who work on live electrical parts either by occupation or just a do-it-yourself (DIY) working on a live house wiring.

The way you stand or the way you access the live parts should be in such a way as to make the duration of contact with the live part as short as possible in the event of accidental contact. Of course, you must at all times de-energize the faulty part before starting on the repair works. However this advise very often are just ignored by some people either because they feel they are skilled enough to work on live parts, or they just don’t bother much with their own safety.

Whatever the reasons are, you can actually position yourself such a way that at the moment of accidental contact, your reflexes will cause your body to break contact immediately. This quick contact break will mean life or death.

About a week ago, a news broke out about a fatal accident involving electrical works has occurred at a project not far from the jobsite I was working on. After some checking, I finally found out what actually has happened that led to the immediate death of the worker. Actually he was trying to cut an insulated electric wire inside a recently completed building. The building has just been handed over to the client and most of the tenants were busy with their own renovations works before they actually move in to the new place.

So the worker was trying to cut a live internal wiring that was supposed to have been dead and isolated by a colleague. As it happened, his colleague isolated a wrong circuit breaker on the electrical DB.

We can talk about isolation procedures in other posts. What I wish to point out here is the way the tool is handled in the case of a wire cutting. The cutter is held with the palm of the hand and a few fingers forming a strong grip. This form of hand action is difficult to let go in the case of an accidental contact.

Some other forms of hand action will more likely result in breaking contact by the body reflexes as the electric shock is sensed. One example is the turning of a termination screw at a circuit breaker terminal using a screwdriver. This sort of issue can be quite subjective and different persons may handle a tool a bit differently. But I think all experienced technicians agree that there is a room there to make the injuries less severe if it has to happen.

The higher the skin contact resistance, the lower the shock current

What does this mean in layman terms? I know these electrical terms can be intimidating to some people. However, electrical safety should be an issue for concern to everyone who use electricity on his or her houses or at their workplaces.

Look at Diagram 1 again. In this case, the girl is almost touching two electrical wires. When both hands touches the wires, the shock current can travel from the left hand holding the red live wire to the right hand holding the black neutral wire.

How much current will actually flow?

That depends on three things. 1. How many volts of voltage at the red live wire; 2. How many volts of voltage at the neutral black wire; 3. How much resistance is presented by the body against the current flow from left hand to the right hand.

Let’s answer this question one by one. For question 1, if you live in London, that voltage may be 220 volts. (Note: Do not get confused by the “volts” terminology. A volt is like speed. 3A or 3 amperes is like 3 meter per second, not like 3 apples per basket.) If you live in Kuala Lumpur, that voltage level may be 240 volts.

However if you live in Los Angeles, your house power sockets will have 110 volt supply. So the red wire there will have 110 volts of voltage.

For question 2: The voltage there will probably be zero volts in all the three cities mentioned above. However there are situations where the voltage at the neutral wire there is not zero. So the neutral wire is not always safe. Always keep this in mind when working on electrical wiring or equipment.

Before we go to question 3, let us do a little bit of calculations first. Since the voltage at the left hand is 240 volts (assuming you are visiting Kuala Lumpur), and 0 volt at the right hand, then the voltage different between the two points is

240 – 0 = 240 volts.

An electrician will call this a 240 volts of potential difference. If the black neutral wire is injured somewhere on the floor, and it touch a live faulty equipment which is at 200 volts, then the potential difference is

240 – 200 = 40 volt, which is a lower value (and hopefully less dangerous).

So how much shock current will flow through the girl’s body if the potential difference is 240 volts (assuming 240 – 0 volts)?

That will depend on how much resistance is presented by the girl’s body against current flow from the live wire and the neutral wire.

So how much is the normal body resistance? This is actually Question No 3 above.

Well, when the skin is dry, the body can present a resistance as high as 100,000 ohms (that is 100 kilo-ohms) against the current flow.

The magnitude of current is lower as the body resistance goes higher. So in this case, the magnitude of the shock current will be:

Shock current = voltage difference divided by body resistance
= 240 volt / 100,000 ohm
= 0.0024 ampere

That is 2.4 thousandth of an ampere of electric current flow, or 2.4 mili-amperes, or 2.4 mA.

How much damage will this amount of current do to the human body? Again you can see the detail list of the injuries in the above-mentioned post. However I listed a few of them here for easy comparison and to help you appreciate the size of this shock current from the viewpoint of injuries that it can cause.

At 1 mA – a normal person would feel a slight tingling sensation.

At 5 mA - A light shock will be felt, but most persons will be able to “let go”. Not a painful feeling, but definitely disturbing. However, a strong reflexive movement by the victim can cause further accidents and other type of injuries.

At 6 to 30 mA - The victim can be paralyzed, or the muscles will freeze (will not be able to release a tool, wire, or other object).

Painful, and my not be possible to let go.

At high voltage (above 600 Volt), this current can already cause severe burns.

As you can see above, at 5 mili-amperes or below, a normal person should still be able to let go the electrified object the he accidentally came into contact with. So a person with dry skin would be less likely to suffer severe injuries if he accidentally comes into contact with a 240 volts live wire. A 110 volts domestic voltage at American house will be less than half of that shock current, so it would be safer theoretically (the American safety follows a different standard so we cannot really compare them apple to apple).

Now let’s see what will happen when the skin is wet. The wet condition can result in a very much lower skin resistance to electric shock current. It can be as low as 1,000 ohms. Therefore the shock current is

Shock current = 240 divided 1000
= 0.24 ampere, which is 240 mili amperes!

From the list that I copied above, at 30 mA the victim would surely not be able to let go of the electrified object he was holding. Therefore the shock current through the body will eventually rise to the maximum that is limited by the body resistance which is 240 mA.

So the victim can suffer a maximum level of injuries. The list on the other post says:

(At 75 mili-Amperes and above – The victim undergo ventricular fibrillation (very rapid, ineffective heartbeat). This condition can cause death within a few minutes. The only way to save the victim is by a special device called defibrillator.

So there you have it. The comparison of the level of resulting injuries between the lowest and the highest skin contact resistances.

BASIC CASES OF ELECTRIC SHOCKS

I started out this post with the intention of explaining about how someone can get electric shocks. But I seem to have spent this far explaining more on the logics of electric shocks.

However, the understanding of the working principles, or the mechanics, behind these accidents will be more useful to you in achieving the most important objective: that is to prevent all serious injuries that result from electrical shocks.

It would be nice to be able to prevent electrical accidents altogether. However as any construction man would testify, it is near to impossible to prevent accidents at construction sites.

The rough environment that a temporary electrical installation is subjected to, the nature of the electrical users at the jobsite, and the difficulties faced by persons responsible on electrical safety on large construction sites to ensure adequate level of safety habits are actually practiced throughout the construction grounds and floors. These three constraints make it near impossible to totally prevent electrical accidents on large construction sites with thousands of workers, especially those with small site areas such as high rise construction at city centers.

What we can do is to minimize the degree of electrical injuries when they do occur.

However, electrical accidents at home or office can still be prevented totally. That is my opinion.

Now THE how to get electric shock No 1. As shown in Diagram 1 at high up in the beginning of this post, that can happen when two locations on the human body came into contact with conductive parts at two different voltages. I have used this diagram to explain the whole upper part of this post above. So that should be enough.

Diagram 2 -Touching live and earth wire


In this case, the right hand came into contact with the earth wire instead of the neutral wire shown in Diagram 1. The result can be similar. I said “can be” instead of “will be”. Why? Because in this case, the live red wire can be installed with an electric shock protection device that will sense this shock current.

The devise is the ELCB (earth leakage circuit breaker). Other names are also used to explain this function in an electrical installation such as RCD (residual current devices), GFCI (ground fault circuit interrupters), etc. Read this post ELCB Circuit to know more how this device functions.

Diagram 3 – When the hand touches a live wire and the person is not separated at the feet from the ground with purpose-made electrical insulation means like rubber shoes, the rubber mat in front of the switchboards in electrical rooms, etc.



Diagram 4 – When there is simultaneous contacts with fault electric motors and ground.



The electric motor can be any electric equipment or appliances. The same process of electric shock current flow will happen.

There are more points that I wish to write down here. However it’s already almost three AM and I have to go to work tomorrow. So I will continue this some other time, in another post.

Stay safe. Electricity kills.

RELATED ARTICLES: a) Home electrical wiring, symbols and checking;

Copyright http://electricalinstallationblog.blogspot.com/ How you get electric shocks

Thursday, October 29, 2009

Lightning protection specifications

The following provides some example specifications that can be used in a contract for the installation of the lightning protection system in a multi-storey office building.

General
The installation of the Lightning Protection must comply with the specifications below, and the information given in the accompanying drawings, but in any case must always be in accordance with the British Standard Code of Practice BS 6651: 1985 and to the satisfaction of the S.O.’s representative. All materials should conform to the latest edition of B.S. Specifications.

Air Termination
Materials for the air termination must be medium or hard drawn copper or phosphor bronze rod of at least 15mm in diameter.

The terminations shall project at least 460mm above the highest point of the building.

They shall be firmly and permanently fixed with saddles or brackets and protected from mechanical damage.

Roof conductors
Materials for the roof conductors must be high conductivity annealed copper tape with the dimensions of 25mm x 3mm.

The roof conductors shall interconnect all air terminations to all down conductors and form a conducting air termination network covering the area to be protected with closed metal loops.

All exposed metallic structures shall be bonded in a solid and permanent manner to the roof conductor network.

Care should be exercised to avoid corrosion by the bonding of dissimilar metals.

Ferrous metals should not be used.

All joints and conductors shall be protected against mechanical damage.

Roof conductor runs shall be as direct as possible with spacer bars or tape clips at two meter intervals.

Bends shall be made as large as possible and in any event the bending radius shall not be less than 150mm.


Down conductors
Materials for the down conductors shall be of high conductivity annealed copper tape with the dimensions of 25mm x 3mm.

Down conductors shall interconnect the roof conductor network to the earth termination.

The route shall not interfere with the architecture and shall as direct as possible.

The down conductors shall be firmly and permanently fixed to the outside of the building or structure with spacer bars or tape clips at one meter intervals.

All independent metallic structures and other building structures within 600mm of any down conductor route shall be bonded to the nearest down conductor.

Lift shafts and duct shafts shall not be used as down conductor routes.

There shall not be any “up-turn” for the down conductor routes.

Joints and bonds
All joints shall be tinned and soldered and double riveted.

Clamped, bolted and screwed joints shall not be used, except at testing points and at rod connections.

Joints or bonds shall be as few as possible. All joints shall be coated with bituminous paint and protected against moisture and corrosion.

The maximum resistance of a joint shall not exceed 0.5 miliohms.

Tape to tape bonding clamps shall be “Furse” type having tinned contact surfaces complete with 8mm phosphor bronze fixing screw.

Test and junction clamps
Materials for the clamps should be phosphor bronze.

Test clamps shall be provided on each down conductor in an easily accessible position for testing purposes at a height of 2000mm from finished ground level.

Test clamps shall be protected from unauthorized interference.

Test clamps shall be provided on the roof conductor network in such a way that all parts of the network can be tested independently.

The test clamps shall be of approved type and shall not constitute an electrical resistance within the system.

After installation and testing they shall be painted with bituminous paint to prevent corrosion.

Earth termination
Materials for the earth terminations shall be of hard drawn copper or phosphor bronze rod. The minimum diameter of the rod shall not be less than 16mm.

The diameter of the rod shall be chosen according to the site condition but it shall always be such that it can be driven into the soil without bending or deforming the rod. Proper driving head and coupling similar to “Furse” type shall be employed.

The length of the rods shall be made up from the standard 1200mm lengths with internal screws and socket joints.

Minimum lengths of earth driven electrodes shall be 2400mm.

The length or the number of rods shall be increased if the maximum permissible earth resistance of five ohms cannot be achieved with the standard electrodes as specified.

The distance between two driven electrodes shall be equal to or greater than their driven length.

When more than one down conductors are used and terminated at earth terminations, all earth rods shall be bonded together to form one network.

The lightning protection earthing shall not be used in whole or in part as part of electrical earthing without the approval of the S.O.

Chemical treatment of soil at termination points to decrease the earth resistance shall not be carried out without the approval of the S.O.

Connections to the earth electrodes shall be by means of approved connector clamps adequately tightened. Earth connections shall be protected from damage by means of suitable electrode housing. The actual connection of the rods must be accessible and clearly visible when the housing cover is removed.

Testing
Testing of earth resistance and conductor continuity shall be carried as specified in the British Standard Code of Practice BS 6651: 1985.

The test shall be carried out in the presence and to the satisfaction of the S.O.

The resultant earth resistance of the electrodes shall not exceed five ohms and this resistance value shall be determined by an Earth Resistance Megger.


Copyright http://electricalinstallationblog.blogspot.com/ - Lightning protection specifications

Friday, July 17, 2009

Temporary Electrical Installations

This post will present you with pictures of temporary electrical installations, the temporary switchboards (at this post, Temporary electrical switchboard), temporary electrical DB, temporary cables and poles.

The post is open ended. I will keep adding more pictures and comments when I find something that I think the readers will be interested in.

Someone also commented that I have yet not uploaded any picture on temporary lighting.

Well, now you have a few of  the pictures at this post,  Temporary site floodlights. There is also more information on site lighting here, Temporary lighting installation.

I have also just sent a new anchor post,  Free electric installation pictures, to partially fulfill a few requests to have all the pics at one place.

So if construction site’s temporary electricity supply is a subject of your interest, keep checking this post every few weeks, you may find new information that you can use.

-----------------------------------------------------------------------------------------------
RELATED POSTS: (a) Electrical DB installation; (b) Electrical injury pictures;

.........................................................................................................................

For readers who have visited this site before, you can see that this post keeps changing. That’s because I need to adjust the layout and some contents here and there so the newly added information can fit in and also to make the various content more coherent.

One other thing, if you have the time, check out the following link. It is a link on how to convert your car into an electric car at minimal cost. It is a way we in the electrical industry can contribute in the global effort to save this planet. In any case, it can save some significant dollars of our daily transport costs. Check it out. It’s a good reading.

Content:

Section A. First case – 20 floors of temporary electricity supply without the electrical grounding.
Picture 1 – Temporary switchboard, temporary DB, temporary cables, temporary extension cords, temporary sockets.
Picture 2 – Another temporary DB (Picture quality not so good. Sorry…)

Section B. Another DB – Temporary electrical panel, temporary cables and extension cords.
Picture 3 – Temporary distribution board – Right view
Picture 4 – Temporary distribution board – Front view
Picture 5 – Temporary distribution board – Left view

Section C. Site temporary electric supply – The risk

Section D. Another case of the electric supply without the earth grounding.
Picture 6 - Electrical panel location (Click on the picture to see full size)
Picture 7- Electrical panel inside view (Click on the picture to see full size)
Picture 8- Earthing copper bar without connection to earth (Click on the picture to see full size)
Picture 9- Incoming 4-core twisted cable without earth (Click on the picture to see full size)


Section E. A simple example of temporary earth
Picture 10 – Temporary electric supply: The complete system
Picture 11 – Temporary cables, temporary meter, temporary distribution board, temporary earth wire and protective PVC conduit.
Picture 12 – Temporary earth grounding


Section F. Site power distribution and equipment

The supply equipment

The distribution system
Picture 13 – Temporary electric poles
Picture 14 – Accidents on electric poles

Section G: Is there a foolproof system for a site temporary power?
The weaknesses of RCD (or ELCB)
Diagram 15 – Three- phase reduced low voltage supply system
Diagram 16 – reduced low voltage supply system (single phase)


Section A. First case – 20 floors of temporary electricity supply without the electrical grounding.


Today I am going to share with you a picture of one of the most important parts of temporary electrical installations in construction works, that is the temporary supply sub-switchboard, distribution board and their cabling.

Below is the picture of a temporary electrical assembly. It was taken at one of my projects a few years ago. What you see in the picture is the floor temporary sub-switchboard, which sits on the left of the assembly. Next to it is the temporary DB with an on-board three phase isolator and a few 13A switched socket outlets.

Picture 1 – Temporary switchboard, temporary DB, temporary cables, temporary extension cords, temporary sockets.

Temporary Electrical Installations Board Image 1

The project was a multi-storey residential building and the temporary supply was taken from the temporary main switchboard at the ground floor. The authority's meter panel was installed at the main switchboard. So the twisted 4-core submain cable was run from the main switchboard to each sub-switchboard at individual floors (one sub-switchboard for every three floors actually). Since it was a 21-storey condominium, seven subswitchboards were installed. From each sub-switchboard, cables were run at high level to distribution boards at various locations at the three floors in its coverage.

Back to the picture… So what is so special about the electrical board assembly in the picture? This is one example of the usual practices in the installation of temporary electrical supply at construction sites in our country. Not all construction sites are like this example, of course. Many job sites practise very good safety standards and I can personally testify to that, but quite frankly the practise shown in the picture is quite common. And in this case I have seen one situation that I have never seen in my entire 18 years of involvement at construction sites. I apologize the picture may not be very clear, but I hope you can see that the incoming cables to the floor sub-switchboard is only four-core. It has NO EARTHING at all.

I joined the supervision team while the work was already quite advanced with only a few month left to the completion. The temporary electrical supply has been in operation for almost a year. The electrical sub-contractor has also been on board for many weeks. Yet the electrical supply distribution from first floor to top floor at Level 21 has no earthing. I was shocked when I notice this on my second day at site. It was unbelievable. Some unlucky workers could have died from this oversight.

The 25 by 3 mm earthing copper tape was finally installed later, after many days of my urging them to do it. The distribution boards and the temporary cabling were also much improved.

As you can see, apart from the earthing conductor, obviously there were a few more things that were wrong with the distribution boards, the cabling and the plug and sockets in the picture. Maybe we can talk again about these in my future posts.

For now I just wish to emphasize the importance of checking the temporary electrical supply installation at your construction sites. Do not assume that the main contractor of a RM230 million building project will have enough people to look at safety matters as important as this one.

More Temporary Electrical Installations

I have also attached below two more pictures of temporary distribution boards just for the fun of it.

Picture 2 – Another temporary DB (Picture quality not so good. Sorry…)

Temporary Electrical Installations Distribution Board Image 2



Temporary Electrical Installations Distribution Board Image 3

These temporary electrical DB are also located along the main access route inside the building under construction. Exposed, without barricade, without any protection at all. This is how you can get electric shocks.

That's it for now. When we meet again I will show you a few more pictures of electrical installations from my previous projects and maybe we can learn some things from them.
That's it for now. When we meet again I will show you a few more pictures of electrical installations from my previous projects and maybe we can learn some things from them.


Section B. Another DB – Temporary electrical panel, temporary cables and extension cords.

These pictures I have already posted on my other blog a few months. It’s a new blog I just set up but I don’t have much time to spare on it. So it’s not drawing much traffic. So I thought I might as well put it here so it can be of some use to someone.

Below you will find a few pictures on a temporary electrical panel, sockets, plugs and extension cords. I have added a few comments below the pictures on aspects that I think is important. Further comments will be added when I think of something readers may be interested to know.

Picture 3 – Temporary distribution board – Right view


Temporary Electrical Panel Image 1
Picture 4 – Temporary distribution board – Front view
Temporary Electrical Panel Image 2
Picture 5 – Temporary distribution board – Left view
Temporary Electrical Panel Image 3


Is there anything wrong with the electrical installation in these pictures? The temporary panel seems to be quite new and definitely in a good condition.

You may question about the mounting method for the panel. But this is a temporary panel for a construction site. At times, the subcontractor needs to move the panel from one place to another every few days. So fixed wall mounted method is not a practical choice this circumstances.

Yes, you may want to suggest that the mounting stand be made of a much better material and design. That I would agree.

The supply temporary cables to the panel seem to be four single core cables. I do not know what size just by looking at the cable from a distance, even though an electrician might be able to give a good guess. Four core means four phases plus one neutral.

You can also see two very good-looking wires with green insulation twisting along the four-cable bunch. These must be the earthing wires, or Circuit Protective Conductor to be precise. Is the total cross section sufficient of the earth wires sufficient? I am a bit rusty on this nowadays. But temporary electrical supply only needs residual current protection as the shock protection. The green wires seem like 4 square mm. Two of them will give 8 sq.mm. I think that should be enough. Of course the required cross section of the earth cables depend on the distance of the temporary panel to the earth electrodes.

That covers the electrical panel and the incoming supply cables. Now let us look at the outgoing circuits from the panel.

First the socket outlets, or the receptacles as the Americans say it. They seem to have the original SIRIM sticker on each of the sockets. In any case all the sockets are new, so there should not be much issue about them. However what has been plugged into each of the sockets is a different matter.

The appliance connected to the right socket of the lower row should be okay. I think it's the charger for a walkie-talkie. All factory-manufactured and all new.

However, the cords connected to the other four sockets may have some serious safety issues. I will add comments on these in the near future.

Have a nice day.



Update Jan. 2010: You can see pictures of 11kV switchboards at my new post Hospital LV Electrical Installation.



Section C. Site electric supply – The risk

It has always been a challenge to provide the electric supply to the site people safely. Construction sites are among the most challenging environments to the safe use of electricity.

A lot of works are done outdoors, in all sorts of weather conditions. Wet and damp conditions present very high risks of severe electric shocks.

The workflow of site works is constantly changing as the construction work progresses. Therefore, the temptations to improvise the electrical distribution system are often too great to resist.

Routine construction activities, the demolition and excavation works may all result in damages to both the temporary supply and the newly fixed permanent supply systems.

When the activities at a site are at its peak with hundreds or thousands of workers (not to mention construction vehicles and machineries), the site usually become very congested. This sort of situations makes the control of risks very difficult. Temporary cables and electric construction tools and equipment are very likely to be damaged by the movement of heavy machines and materials.

The people who use electricity at site have various needs, and sometimes conflicting interests and expectations. The workers and team leaders themselves work for different subcontractors and suppliers. In order to maintain any reasonable degree of safety and control of risks, a effective site management is an absolute must-have for the site main contractor or the client’s people who are in charge at the construction site.

Due to the nature of construction works, a risk-free environment is impossible to attain most of the time. However, some risks can be avoided by careful planning before the work commences at the site.
-------------------------------------------------------------------------------------------------

Section D. Another case of the electric supply without the earth grounding.

This is another case of missing electrical grounding that I already published in my other blog.

The following pictures of a temporary electrical panel show another common type electrical hazard at construction sites. I took these photos at a building construction site about four months ago.

This panel was located under a shade at the concrete mixing station of the construction site. As you can see, the location of the electrical panel was full of water. No, it was not due to rainwater. The location was always that way, because the plant consumed a lot of water daily. The situation presented a very high risk of electrocution not just to the worker operating the concrete mixing plant, but also to other workers.

Someone at the site told me that the electrical panel was too high above the water. So there was not really much risk. What do you think?

Picture 6 - Electrical panel location (Click on the picture to see full size)


Electrical Panel Image 1


I opened the electrical panel door to check inside (See Picture 7). The panel was a good quality and relatively new. The internal wiring inside the panel was also done nicely and it was neat.

But wait.... Where is the earthing to the panel? There was good earth wiring inside the panel - the green wires. All neatly run and properly terminated to the copper earth bar. However, the connection just stopped there. There was no outgoing connection to earth (See Picture 8).

Picture 7- Electrical panel inside view (Click on the picture to see full size)

Electrical Panel Image 2




Picture 8- Earthing copper bar without connection to earth (Click on the picture to see full size)
Electrical panel Image 3


I checked the incoming twisted cable. It was a four-core. No earth cable anywhere (See Picture 9). I checked around the panel to see if the person who installed it used a different conductor and run it direct to earth somehow. Nope, no other conductor installed.

The conclusion? The electrical panel was not earthed at all. So what happens when there is a considerable leakage current? What protects the worker at the concrete mixer machine there, especially with the wet condition there? Sadly to say... no protection at all.

Feeling exasperated, I checked inside the electrical panel again. Surprise... there was not even an earth leakage circuit breaker there, or any other type of residual current protective device.

Picture 9- Incoming 4-core twisted cable without earth (Click on the picture to see full size)

Electrical Panel Image 4


I have to go now. I will add more info to this post in the near future. I know there are questions in the minds of some of the readers relating to the electrical installation shown in these pictures. The electric shock protection issue can be tricky sometimes.

Until next time...

Section E. A simple example of temporary earth

The safety of an electric supply often depends on the existence of an effective earth. It is the responsibility of the person in charge of the construction site to ensure that the earthing of the electric supply system is effective. The site’s electricity supplier (the electric supply authority) has nothing to with this part of the electric supply.

Many electricity supply authorities use protective multiple earthing (PME) system. In this system the electrical system’s neutral and earth are combined. When this system is used, all metalwork including structural metalwork must be bonded together in such a way to make all metal parts electrically continuous.

However in most real life construction sites, this bonding is hard to do and almost impossible to maintain properly throughout the duration of the construction period. So usually, the public utility supplier will not connect the supply until an alternative electrical earth is provided and fully tested. They also insist that evidence of the earthing test results endorsed by a competent electrician is submitted together with the completed application forms for the temporary electricity supply to the site.

Several methods are used to provide the alternative electrical earth. The most commonly used method is to use an independent earth electrode installed at the location near the main intake temporary switchboard (this is usually the location where the temporary meter is installed). This will ensure that the protection fuses will operate and disconnect the site electrical installation from the incoming public supply in the event of a fault. This disconnection is an absolute must in order to minimize the damages to the site’s electrical system due to the fault and also to prevent the fault from spreading upstream to the electric supplier’s distribution network. The latter is the main reason the electricity supplier is worried about this aspect of the temporary installations.

Picture 10 – Temporary electric supply: The complete system


I will devote one whole post in the future for this subject of earthing. But for now I have a few picture of temporary electrical grounding for your viewing pleasures. I seek an apology from those readers who already have some electrical knowledge. These pictures are not for you guys. They are too simple. However for those managers and construction people who have always been intimidated by those colleagues on these sorts of issues, let me assure you that if you understand what these three lousy pictures say, then you already understand what an electrical grounding is.

Picture 11 – Temporary cables, temporary meter, temporary distribution board, temporary earth wire and protective PVC conduit.


Picture 12 – Temporary earth grounding


Now lets start with picture 10 (You may need to click on the picture to see it in full size). The black case on the wooden panel there the temporary electric meter supplied by the electric authority. Below it in white PVC casing is the temporary distribution board. You can also see coming out downward from the distribution board a piece of wire in green insulation and this wire goes straight into a two meter length white PVC conduit, and (if you watch it closely) it comes out of the vertical PVC conduit at the bottom and goes straight into the concrete floor just beside the plywood partition wall. All these you can see much more clearly in Pictures 11 and 12.

Back to the black energy meter. Above it you can see two lengths of black insulated cables coming down from high level (below the roof level of the temporary wooden structure). One cable terminates at a black piece of component just above the meter, while the other one terminates at a cheap white plastic terminal block. The two components each have a cable of the same size coming out at the bottom connection and terminate at the temporary kilo-watt-hour meter.

Now lets get a little bit more technical. This is what we call a single-phase electrical installation (a three-phase supply would have four black cables coming down from the roof level – three phase cables and one neutral cable). So the incoming supply from the authority is also a single phase supply (we apply single-phase supply, so they give us a single phase supply).

An electric supply from the authority can be one of a few types. The type as recorded in the pictures is the single-phase two-wire type (three-phase 4-wire if we apply three-phase supply). This type will have two incoming cables from the authority’s distribution network – one live or phase cable and one neutral cable. Other types may have three incoming cables from the distribution network for the same one-phase supply – the same live and neutral cables, plus a third cable, which is the earthing cable.

Now as I said earlier in this post, a construction site really needs an independent and reliable earthing, an electrical grounding that is not dependent on any third party’s grounding or even the electricity supplier’s grounding. Failure to provide this can result in fatal injuries from electric shocks, even multiple casualties in a single accident. Never mind my emotions on this (if you can sense them), but an electrical accident is that dangerous and electrical shocks can strike silently without warning.

Because of the need for that independent and reliable earth for the temporary site supply, the green electric cable is installed below the white PVC distribution board (Picture 11 shows this clearly). Without this cable, the electrical system can still work. The workers can still use their tools and do a good job for their employers so the construction venture can end up being very profitable for the shareholders of the company. But one fine day, an extension cord that carries current to the electric drill one of the workers has been using gets injured, exposing the live wire to an unintentional contact with any of the workers around the area. Being hard at work, the workers bodies and clothes are usually very damp or very wet with sweat. One accidental contact at any part of a workers body with the exposed live conductor of the damaged extension cord, then you will severe electric shock injury, even death is highly likely depending on where on the worker’s body the contact to the live wire happens. If the contact is at the hands, then the electric shock current will travel through the chest and the workers heart before going down to the legs and the ground. Then you may have a case of fatal injuries there.

Sorry for the diversion. This electrical earthing matter is so simple that I have to drag the stories into the injury aspects to make it a bit longer ;-)).

Not only it is simple, it is also plain cheap and low cost. Look at the picture again. You have a short length of the green wire and two meters of the white PVC pipe. Wait… I know what a few of you are thinking… Yes, there is copper earth electrode in the concrete, which goes straight down below the concrete about 1.5 to three meters into the ground.

The example that I use here is a very small installation, so it looks simple. This wooden structure only uses a few amperes. However even for a large installation, the grounding is relatively just as simple.

The point that I am trying to make in this section is that providing an independent and effective earth is not a challenge at all in most situations. So, do not risk human lives just to save some construction cost there.

Section F. Site power distribution and equipment

The supply equipment

Equipment selected for use in a site temporary electric supply distribution need to be designed for use in the environment it in is going to be operated in. During the selection process, the most important is to make sure that the manufacturer’s restrictions of use are considered. For example a sub-switchboard that need to be moved frequently, left exposed under sun, and rain during operation must necessarily be of adequate IP rating.

The construction of the equipment must also be robust enough to withstand the damage caused by the rough treatment at the construction site.

Most of the time, equipment purchased for use at a project site will be transported for use in another project or work locations. Therefore, it needs to have provisions for frequent loading and unloading, transport and storage while throughout all these it cannot be damaged to the point of becoming malfunction and unsafe for use. Under the pressure of worksite demands, even a good site electrician tends to improvise on the safety aspects site electricity supply. With damaged equipment, the risks are compounded even more.

The equipment selected also shall include the provision for isolation of supply and facilities for locking the switches. This is especially important main switchboards and sub-switchboards where the locations of the board and the local distribution boards are quite far away and not within the line of sight.

The distribution system

The distribution system is the system of cabling and equipment that are arranged to distribute the electric power to the various machines and current using locations throughout the construction site. This temporary distribution system will be removed after the construction work is completed and the permanent power supply system is commissioned and operational.

The location of the switchgear and metering apparatus must be secured in terms of security from unauthorized access and safety from damage and the effects of the environmental factors. Access to the switchgears and the main isolation switch must be accessible at all times in case of emergency.

Just because the supply system is temporary does not mean it can be assembled without all the proper engineering calculations and considerations required of a permanent system. Fuses, circuit breakers and cables all must properly selected and sized.

Many practices shown in the pictures of temporary installations above are bad practices. If contractors are allowed to provide these bad installations on site power supply, accidents whether in the form of damaged equipment, fires or electric shock or even electrocutions is bound to happen sooner or latter. Makeshift arrangements such as unprotected wiring, twisted or taped cable joints are often dangerous and cannot be accepted. All the temporary installations works must be done in accordance to the appropriate standards.

Site distribution cables must be properly located. They should not be installed where they are likely to be damaged by the construction activities or vehicles. Picture 13 below shows an example of a site distribution cabling running on temporary electric poles. This method of installation is fine but here they are run across one of the main road within the construction site. The next picture (Picture 14) shows the temporary cables on the ground. Only a few minutes earlier, an earth moving tipper truck accidentally hit and dragged the overhead cable while unloading the earth for a drainage work next to the temporary poles. There were workers nearby when it happen, including me. Luckily, no one was injured.

The above accident could have been prevented if the stretch of the cables crossing the construction have buried in a G.I. pipe just two or three feet below the road. With all the construction machineries at the site, these could have been done in a matter of one or two hours. However, here the main contractor chose the easy way and just installed the whole stretch on poles.
Picture 13 – Temporary electric poles

Picture 14 – Accidents on electric poles


Section G: Is there a foolproof system of site temporary electricity?

RCD (or ELCB)

RCD (residual current devices) or ELCB (earth leakage circuit breaker) is not an ideal device for use in the tough environment of construction sites. It may not even be possible to maintain the integrity of the housing where the RCD devises are housed in.

It is also not the kind of devices that can be fitted on portable equipment, which usually are subject to mechanical shocks and vibration.

Electric shock protection based on RCD alone has many weaknesses. It cannot guarantee safety.
a) When an RCD malfunctions or it fails to operate, this failure can go unnoticed so the affected workers are unaware of the dangers awaiting to turn into accidents.
b) The RCD only protect against faults to earth, and it required sufficient bonding to earth for operation. It cannot operate when there is no earth connection, for example, when current passing from live to neutral. This type of situation is still dangerous: the workers can still get electric shock, injuries or even electrocution even though the RCD is working properly.
c) The use of RCD will not make the system safe if it is not properly designed, properly installed and adequately maintained. The popularity of RCD may have been due to difficulties to obtain low earth resistance on many installation conditions. However, RCD is not a substitute for reliable and efficient earth grounding.
d) RCD designed for electric shock protection have a rated tripping current of 30 mA. At sites where temporary load requirements are higher, installing a 30 mA at the point of intake (like an ELCB installation in a house distribution board) will lead to frequent unnecessary tripping, shutting off the supply to the whole site.
e) Electrical loads at construction sites consist of tools and equipment that have high leakage currents. This factor has led to many ‘nuisance’ tripping of the supply. These are also unwanted tripping that frequently lead to the RCD devise being defeated in some by the workers involved, leaving the whole supply system with a shock protection.
f) RCD can be chosen to be very sensitive to small current leakage, and trip fast enough to avoid serious injuries. However, with this principle, it only limits the duration of time that the current flows in the event of shock, it does not limit the magnitude of the current flowing. If the devise fails to operate, the current will continue to flow continuously. Even low shock current if allowed to flow continuously through the body can cause serious injuries.

Reduced Low Voltage supply

Most of the time the electric shocks that occur are between the live parts and earth, which are the results of damaged cable insulations, faulty power plugs, or faulty or damaged equipment. Whatever is done to the electrical system, or the electric shock protection to reduce the risk of shock to people, the potential is always there. RCD itself is a active electromechanical system that can fail. It effectiveness requires an effective earth which can be hard to maintain in a real life construction sites. While the scope of protection covered by the device still have gaps, that is left without shock protection (between live and neutral).
Fortunately, there is one system that has been proven almost foolproof against electric shocks at construction sites. It is called the reduced low voltage system, where the supply voltage is stepped down to a level which is practically safe without depending too much on an active shock protection, or a sophisticated system that is hard to implement at construction sites.
This system reduced the 415/ 240 volts supply voltage to 110/64 volts for a 3-phase supply. If only 1-phase supply is needed, then a 240/ 110 volt center-tapped transformer is used to reduce the single phase voltage to 110 volts with the electrical grounding connected to the center of the secondary transformer coil. This will present a maximum possible risk of only 55 volts to the users of the electricity instead of 240 volt (or 415 volts for 3-phase) as I the original 415/240 volts supply.
Technical studies that have been carried out have shown that the maximum indirect contact touch voltage to earth is only 40 volts. This is below the danger voltage as specified by the IEE Regulation. Even the SELV (safety extra low voltage system) as specified in the regulation is 50 volts.
The following diagrams show the basic configuration of the reduced low voltage supply system.

Diagram 15 – 3-phase reduced low voltage supply system


Diagram 16 – single-phase reduced low voltage supply system


(c) copyright http://electricalinstallationblog.blogspot.com Temporary Electrical Installations

Monday, July 6, 2009

Lightning Protection System: An Overview

From the outset, a lightning seems far removed from an electrical system. Yet the protection from lightning strikes and from the damages caused by surges due to lightning strikes is an integral part of any electrical installation.

Men since the ancient times believed that a lightning strike was a demonstration of God's power, which He used as a weapon to punish those who commit great sins on earth.

Whatever the truth is, men today has developed a far more advanced knowledge and technology with regard to the lightning strikes and their effects than their ancient ancestors. Yet throughout the world the lightning strikes cause countless fatalities and material damages. Either through ignorance or an insufficient understanding of the principles underlying the theory and the practice of lightning protection.

Seen from the perspective of a building structure, lightning protection generally consist of 3 sections: aerial conductor network, the down conductors, and the earthing system. By design, the function of the aerial conductor network is to present at the highest point of the structures an area that will attract the lightning strike away from other parts of the building. The current of the strike will then be routed down through the down conductors to the earth grounding rod at the ground level or the lowest level in multiple basement structures.

The purpose of the earthing part is to help dissipate the discharge of the 200 kilo-ampere electrical energy into the earth mass as quickly as possible. This is very critical to the performance of the whole system, because a lower rate of dissipation will expose a higher risk of injuries or fatalities due to gradient voltage. Also damage to properties from flashover to ungrounded nearby metal parts.

Aerial Conductor Network

The aerial conductor network is designed to basically attract the lightning strikes. It is supposed to be where the lightning will strike when they attack a building structure. Therefore the aerial conductor network must be installed at the highest floor of the building structure.

Basically the intention is to create a network of conductors so that no point on the roof is more than five meters away from the nearest conductor of the network. Where a structure is raised above the roof level of a building (eg. lift motor room) then that part of the structure shall have their own aerial network conductor which shall be properly bonded to the overall buildings lightning protection scheme.

With the popularity of the new technology of lightweight all-metal roofing system, questions often arises whether the whole metal roofing system can be bonded to and form part of the lightning protection system without the need for a separate aerial conductor network.

Theoretically "Yes", these metal roofing system scan be used as the aerial conductor network and they have been practically installed to also serve that puspose for a while. Even though in many cases the aerial conductor network are still installed as a precaution.

However the development in the metal roofing system has resuled in the use of very thin roofing sheets that they require some form of metal parts to hold them together and to the roof structure. The effect is basically a complete isolation of a sheet fro the adjacent one, and to the roof structure. In these cases it is absolutely necesary to install a separate aerial conductor network.

Down conductors

The down conductor carries the 200kA electrical surge straight down to the earth mass. Due to the magnitude and the extremely steep front of the electrical surge, the current must be carried to the ground by the shortest possible route. Failure to do so will increase considerable the risk of side flashover.

The down conductor should be arranged to spread as uniformly as possible around the perimeter of the building at approximately 20 m spacing. They must follow the most direct path to the ground with a minimum number of bends. In difficult situations like at parapet walls, a loop-around turn must be avoided to prevent flashover. At 1.5 meter above ground, a test point must be provided at each down conductor. Here a bimetallic connector must also be installed if aluminum is used as the down conductor and the conductor below the test point to earth is copper.

Below the 1.5m test points, until terminations at the earth terminals inside the earth chambers, the down conductors must be installed inside a PVC pipe to protect it from the effects of corrosion and damage. Also to prevent a person or other metal parts from touching the conductors during lightning strike.

Copper used to be the conductor of choice for the whole lightning protection system including the down conductor in this country. But in the last ten years many engineers turn to aluminum for all parts above the test points. Parts of the reasons are the rising cost of copper materials. The other reason is vandalism. The vandalism factor is highly dangerous to the integrity of a lightning protection. This is due to the fact that it operates in silence and it is generally maintenance-free. A missing part at a few down conductors may not be noticed until the damages have been done.

This brings us to the very reason a lightning protection system must be regularly inspected. It will also ensure i is providing optimum protection. This will also check if there are other metal works within the flashover distance that is not properly bonded to the system.

Earth electrodes

The down conductors are routed along the most direct path to the ground and terminates to the lightning protection earthing system. These earthing systems usually steel reinforced copper rod half an inch in diameter, and driven a few feet deep into the ground.

Other methods are also used instead of the deep driven steel rods to provide the best possible contact with the earth mass. The choice depends on the prevailing ground conditions: the soils resistivity and the soil moisture content.In urban areas, a few earth rods are installed first and their combined resistance is measured. More rods are driven and connected until the 10-ohm requirement is met. However in locations away from recent developments, the soil conditions are not known. So the soil resistivity tests must be carried out to determine the earthing method most suitable and the extent of the work required.

At times when the soil is sitting on rocky subsoil below ground, a hole has to be drilled down 100 m or more and a long copper rod inserted deep into the hole to get the 10-ohm requirement. In more extreme cases, even this is not enough and soil conditioning agents like Bentonite or conductive cement need to be used. These compounds are prepared as a slurry or mix, and poured down the vertically drilled hole, creating a lower resistance between the embedded copper earth electrode and the surrounding soil.

The performance of a lightning protection is only as good as it weakest link. Any weakness along the flow path of the surge from the aerial conductor network down to the earth chamber can cause a side flashover to the building structure. A flashover means the surge current has taken an un-controllable path to the ground, causing damage to properties and possibly injuring persons along the way.Therefore it is vital that a lightning protection system is inspected properly and regularly. Recording of the tests must be done according to the latest international standards.

By the very nature of lightning strikes, no international standard can guarantee a total protection from their strikes. However, by obeying the latest international standards, we can ensure that the risk of damage and danger to human lives has been reduced to minimal.

Home Electrical Installation - How it works

In this article I will explain the skeleton of how a home electrical installation works. The content of this article is very basic. It is not for technicians or engineers. It is for those people who have been using electricity all their lives without knowing at all how it works, how it causes fire or how it kills people.

The electrical current that goes into our homes come from the electricity supply company's distribution network, usually in the form of overhead cables running on concrete poles or using cables buried one meter below the ground. When the cables reach a residential house, they usually enter the house through the front entrance and connect to a meter panel. Together with the meter on the panel is also a cut-out fuse. The meter and the fuse usually belong to the supply company. From the meter panel the electrical cables go to the home distribution panel. On the panel are usually an isolation switch, a leakage protection circuit breaker and a few outgoing fuses or outgoing circuit breakers. From the outgoing fuses or circuit breakers the wiring cables run above the ceiling, inside or on the surface of the wall, or concealed inside the concrete floor to go the lamps, ceiling fans, socket outlets and other equipment like the toilet exhaust fans in our homes.

When a home user connects an electrical appliance to a socket outlet, the connection is usually made by the use of an electrical cord. One end of the cord has a plug unit (sometimes the plug unit contains a fuse) that is inserted to the power socket (i.e.wall plug). The other end will be plugged to another socket already built-in on the appliance. Now and then the location of the electrical appliance need to be quite a few meters away from the wall socket outlet. The electrical cord provided with the appliance is usually between one to one and a half meters long. In these cases home users usually purchase an extension cord to connect between the wall socket and the appliance's electrical cord.

From the viewpoint of the electrical current flow, the supply uses only two wires. That is why in some countries or regions we can see only two big wires coming down from the electric pole to a house. One of them is called the live wire, "hot" wire or phase wire. It is this wire that is "dangerous". The second wire is called the neutral wire or the "return" wire. The electric current flow into the house will come out again (i.e. return) in the same magnitude and goes back into the supply company's transformer or generator. This electrical path forms a complete "loop", like a circle. The continuous and circulating flow of this electrical current is what makes the filament inside the house incandescent lamp burns and produce light that brightens our house. This behaviour of the home electrical system brighten and enrich our lives. When used and handled properly, electricity is very useful and friendly. It is however very powerful and dangerous, and therefore must be treated with respect.

With the two wires described above, we can have electricity in our home that can keep our food fresh in the refrigerator and replace the candles to light up the house during the night. However with just these two wires, it is like driving an car at high speed without the brake. Driving the car without a brake is extremely dangerous even on an empty freeway that has no traffic light for hundreds of kilometers at three in the morning. As in driving, we need to step on the brake now and then to slow down, or during an emergency.

In a home electrical system, this braking is accomplished through a third wire, the earth wire. Many electrical terms are commonly used for this wire such as earthing wire, ground wire, chasis wire or protective wire. In a house, this earth wire is almost always colored green or green with yellow stripes. The wire connects the metal casing of the electrical appliance in our homes to the "earth body". (Really, it is actually connected to the huge mass of the earth.) When the "hot" or live wire somehow come into contact with the outer metal casing of your washing machine, for example, then the fuse at the distribution board will immediately blow, stopping the current flow to the metal casing of the washing machine so we do not get the shock, a fatal shock actually. Where the distribution board uses a circuit breaker instead , the circuit breaker immediately trips, cutting off the supply just like the fuse does.

If the green wire is broken, or it does not connect properly along its path to the earth body, then the electrical power has no brake. The person touching the washing machine's metal casing can get electrocuted.

So do treat the electrical wiring and electrical appliances in your home with respect. Safety comes first. In future articles I will explain more on the "earth wire" and I will also give more tips and techniques on how to make sure your home electrical installation is safe for you and your family.